Dear Gurus
I have got a scenario in Preventive maintenance area.
Strategy = Workhour
Scheduling Indicator = Activity
Strategy Unit =H
Call horizon=37%
Factory calendar is not assigned
Maint Packages used in Equipment task list are=
Operation 0010 is marked for package one i.e.6000 H
Operation 0020 is marked for package two i.e. 10000 H
Operation 0030 is marked for package three i.e.18000 H
For the Equipment counter info
Annual estimate = 8760.00H
Activity per day =24H
As on today last counter reading reached =6000.00H
Maintenance plan scheduling parameters
Call horizon=37%
Scheduling Period is 5YRS
Completion Requirement is not marked
After Scheduling this maintenance plan I have got following results.
Call no. Planned Date Call Date Difference in days Due Package
1 20.02.2014 completed call n/a 1
2 05.08.2014 22.04.2014 105 2
3 28.10.2014 05.09.2014 53 1
4 05.07.2015 28.01.2015 158 3
5 26.09.2015 05.08.2015 52 2
6 11.03.2016 27.11.2015 106 1
7 16.11.2016 11.06.2016 158 2
8 24.07.2017 16.02.2017 158 3
9 06.01.2018 23.09.2017 105 2
10 31.03.2018 06.02.2018 53 1
Actual Requirement is get the call date for all maintenancd order i.e. 158 days before plan(actual start date) date.
This time required is for procurement of materials and alocation of resources.
To achieve this requirement what settings i need to correct.
Thanks and Regards,
Rahul