Planner groups
Hi ,Team Planner groups which we are using in PM Order and planner groups in tasklist , what is the difference. In my case , I have one planining plant and one maintenance plant. and two departments...
View ArticleCustom screen in IW22
Hi.. Our Requirement is when a particular user status is set a button should appear in notification screen and on pressing the button a pop-up screen should appear to enter the maintenance details.
View ArticleAssembly column in the confirmation screen
Dear PM gurus. Assume that in an equipment there are N no of assemblies, they need to carry out different operations on different assemblies.1. How to map this in a single order.2. Client requirement...
View ArticleAfter activating function LOG_EAM_OLC no time confirmation (IW41) on work...
Hello, maybe somebody can assist here. Business function LOG_EAM_OLC has been activitated, planned costs and actual costs could be posted on work order operation level, but it is not possible to use...
View ArticleDoes DMS offer version management functionality
Hi all,My client is currently using DMS to store documents and accessing it either from SAP or directly from the DMS server "Vault". I hear discontent on the version management. Is this something we...
View ArticleCustomizing Notifications to handle incident reporting with SAP Personas
Hi All,Currently my client is handling all kinds of safety related incidents in Lotus Notes. Requirements:1. The template they fill should be stored in the long text of the Notification in exactly the...
View ArticleProblem in cost tab for Refurbishment Order
Hi, Goods Receipt cost head is not coming in the cost tab for refurbishment order after completion of the goods receipt by using the transaction IW8W.Normally for refurbishment order we will get two...
View ArticleStartegy and Package sequence (unregular cycle)
G'Day All , We have a unique requirement from our client . Our client does the same preventive maintenance work every 3 weeks , 6 weeks and then 10 weeks .As this sequence is a legal requirement ( we...
View ArticleLoading PM Orders via LSMW
Please help me.I want to load PM Orders, but I don't want to use recording (LSMW), because it's too difficult to load substructures.The way, that use recording, need in a few recording.Is there another...
View Articlepm strategy based report
Dear experts I am ravi sap pm consultant I have created a strategy based planning for an equipment with 3 packages . i want to know whether at a particular date what is the status of the maintenance...
View ArticleMaintenance of multiple similar equipment
HI Experts, Need help on maintenance of multiple similar equipment e.g. similar Pumps in 100s of qty. Requirement is to trigger the periodic Preventive maintenance of such pumps at a time. I've...
View ArticleCounter reading transfer to system
Hi Experts, I want to implement the counter based maintenance, wherein the counter's reading need to be read every day manually at fixed timings.My client is a process industry having a complex...
View ArticleAnnual Shutdown maintenance
Hi All, Can planning and scheduling process of annual shutdown maintenance which is normally carried out using Primavera / MS project software be mapped in SAP PM or SAP PS ? How can we do planning...
View ArticleService Order Billing with DIP Profile
Hello All, I have got a requirement where Quantity only to be transferred to Billing Request through DIP Profile. Scenario has been explained in detail. Company is providing Service to the Customer by...
View ArticleCan we see the entire organisation structure by using a T-Code????
Hi All,I am new in sap PM i want to see the Enterprise structure by using a T- Code, is it possible or not suggest me for plant Maintenance. Thanks and Regard,Bikas Pathak
View ArticleDoes DMS offer version management functionality
Hi all,My client is currently using DMS to store documents and accessing it either from SAP or directly from the DMS server "Vault". I hear discontent on the version management. Is this something we...
View ArticleIK12-Reversal Indicator
Hello allI need to remove the access of few users in my company to Reversal: SET/RESET functionality available in change measurement document transaction IK12. I want to achieve this using...
View ArticlePlan Date Calculation on Performance Based PM Scheduling
Dear EAM Expert, Presently, we have implementing Preventive Maintenance using SAP-PM.The Preventive Maintenance Scheduling is using Performance Based (Hours) of Equipment.But, now we are confusing...
View ArticleTo Configure the SAP Plant Maintenance.
Hi All, Need to know,how to configure the SAP PM ( Plant Maintenance ) from scratch. Thanks,Manjunath
View ArticleLinking DIR with PRT object within a Task List
Is there a way to link a DIR to PRT object ? I create a DIR and by using the Object Link tab I would like to link it to PRT object used in Maintenance Task List under an operation.The opposite way is...
View Article