Dear PM experts,
I am creating a custom report for next due date for a maintenance plan number. Next due date refers to the next Planned date which is having the status of "Scheduled Hold" or I need to fetch the Planned date of the Call number from maintenance plan which is yet be released but its previous Call number has been released.
Example : Maintenance plan 111111 has 3 Call numbers and its status are given below from transaction IP10
Call Number Planned date Call date Completion date Scheduling type/ Status
1 06.11.2014 06.11.2014 New start Called - Call number released and PM order created
2. 06.12.2014 06.12.2014 Scheduled Hold - Call number yet to be released
3. 06.01.2015 06.01.2015 Scheduled Hold - Call number yet to be released
Now in the report, i want to fetch the "Planned dates" of the earliest Maintenance call number which is not released
Please suggest me how to fetch this data for this issue
Regards,
J.Balakrishnan