PM Order Basic Start & End Date

$
0
0

Dear friends,

We have ECC 6.0 version since 2007

 

Our user recives Notification from trom the operations as below:

Notification Required Start Date is  say 20.07.2013  &  End Date is  30.08.2013

 

When Planning Creates Order  say on  28.07.2013 from the Notification, the above dates are copied in the Orders and the Basic start dates becomes as  20.07.2013 & End Date 30.08.2013.

But our user wants that the Basic Start date of the Order should not copied from the Notification. But it should be as current date when Order created.

 

We have configuration for PM module for Maintenance Order as

Maintenance & Service Order------General Data ----- Activate basic date as current date for PM Order

Here we keep BLANK. Because our PM preventive maintenance plans are running for future planning where as per plan, date should be there future dates according to the frequency.

 

We have follwoing in SPRO

Maintenance & Service Order --- Scheduling ----Set scheduling Parameter --- 

Adjust Dates ---   Do not adjust Dates

Scheduling Type   --  Forward.

 

We tried to keep  --  Scheduling type as   -  Current Date.

Then any time if Order need to Start after one week, the Basic Start Date will be current date only.

 

Screen attached.

 

Please advise.

Thanks

Jayant Joshi - GPIC- Bahrain