Dear friends,
We have ECC 6.0 version since 2007
Our user recives Notification from trom the operations as below:
Notification Required Start Date is say 20.07.2013 & End Date is 30.08.2013
When Planning Creates Order say on 28.07.2013 from the Notification, the above dates are copied in the Orders and the Basic start dates becomes as 20.07.2013 & End Date 30.08.2013.
But our user wants that the Basic Start date of the Order should not copied from the Notification. But it should be as current date when Order created.
We have configuration for PM module for Maintenance Order as
Maintenance & Service Order------General Data ----- Activate basic date as current date for PM Order
Here we keep BLANK. Because our PM preventive maintenance plans are running for future planning where as per plan, date should be there future dates according to the frequency.
We have follwoing in SPRO
Maintenance & Service Order --- Scheduling ----Set scheduling Parameter ---
Adjust Dates --- Do not adjust Dates
Scheduling Type -- Forward.
We tried to keep -- Scheduling type as - Current Date.
Then any time if Order need to Start after one week, the Basic Start Date will be current date only.
Screen attached.
Please advise.
Thanks
Jayant Joshi - GPIC- Bahrain