Hi ,
Iam having aissue in DIP profile.
I want to determine the material based on Activity type and Work center.
Eg if ACT1 and WC1 means MAT1
if ACT2 and WC2 means MAT2
I have flag the check box for ACTIVITY type and Workcenter for material determination in ODP1 and assigned values in Criteria in the same ODP1 .When I run DP90,system is throughing error message as CHARACTER COMBINATIONS W/O MAT.ASSIGN IN DIP PROFILE XXXXXX.
I think I need to assign the activity type in WC.But my settings in WC are standard value key is SAP0,Capacities OTHER FORMULA SAP008 ,Scheduling OTHER FORMUAL SAP004,In COSTING tab I have given SAP008 in the RHS corner.
How to assign specific Acitivity type to WC.
Regards
KRISHNAN