Capacity planning in PM Order

$
0
0

Hi,

 

Here there is a scenario for my client as follows.

 

We are doing maintenance activity in a plant, and there is a necessity of capacity planning.

 

In work center the start time and end time are mentioned as 09:00:00 and 17:00:00 (total 8 hrs er day).

 

After that we are using this work center in PM order in for an operation duration 10 hrs.

 

So while scheduling, if capacity is over loads, the distribution is taking place as 5 hrs for the first day and the remaining 5 hrs for the next day.

 

Ideally it should be 8 hours in first day and 2 hours in next day.

 

I have mentioned distribution key as SAP000 in WC capacity screen. But no change of distribution.

 

I dont know where and what I missed.

 

Please guide me to get the capacity distribution with 100% utilization of capacity.

 