IW37N operations to planning board

$
0
0

Hello Experts

 

I need your help on Capacity Levelling configuration.

 

We have configured the system such the the operations are pull to planning board from IW37N

User goes to IW37N - gives his specific criteria and executes.

After executing, he pulls them to planning board.

 

When user runs IW37N - the orders and operations are getting generated as per the selection criteria specified in IW37N (Say for example, selected based on a specific operation user status).

When the data is pulled to planning board, we observe that all operations in the order are pulled up.

Say, one order has 3 operations out of which 2 have user status RTS (ready to schedule) and one doesnt have. In IW37N report - we see only 2 operations  -which is correct

 

but when same data is pulled to planning from IW37N - all 3 operations appear in planning board - this is NOT the requirement?

Why is it behaving like this?

 

Any Ideas.....Please help...its urgent!

 

Regards

Pavan