Dear All PM Guru's
I have created the maintenance plan with the following details.
Cycle: 1 month
Call Horizon: 80%
Scheduling Period : 365 days
Start of Cycle: 30/12/2014
Scheduling indicator: Time-Key date.
After scheduling plan scheduling overview list is as below
1 | 01/30/2015 | New start Save to call | ||
2 | 02/28/2015 | Scheduled Save to call | ||
3 | 03/28/2015 | Scheduled Save to call | ||
4 | 04/28/2015 | Scheduled Save to call | ||
5 | 05/28/2015 | Scheduled Save to call | ||
6 | 06/28/2015 | 06/22/2015 | Scheduled Hold | |
7 | 07/28/2015 | 07/22/2015 | Scheduled Hold | |
8 | 08/28/2015 | 08/22/2015 | Scheduled Hold | |
9 | 09/28/2015 | 09/22/2015 | Scheduled Hold | |
10 | 10/28/2015 | 10/22/2015 | Scheduled Hold | |
11 | 11/28/2015 | 11/22/2015 | Scheduled Hold |
12 | 12/28/2015 | 12/22/2015 | Scheduled Hold | |
13 | 01/28/2016 | 01/22/2016 | Scheduled Hold | |
14 | 02/28/2016 | 02/22/2016 | Scheduled Hold | |
15 | 03/28/2016 | 03/22/2016 | Scheduled Hold | |
16 | 04/28/2016 | 04/22/2016 | Scheduled Hold | |
17 | 05/28/2016 | 05/22/2016 | Scheduled Hold |
The according to plan the first call is generated on 01/30/2015, second call is generated on 02/28/2015 coz February month will not be having 30th date.
My question is on from third to last call why system is generating call object on 28th day.
Please help me on this.
Regards
Kiran Ambi