Hi Gurus,
I will appreciate the help in these question :
Q1 - Can you explain to me how can i change the scheduled start and the sched. Fin in the maintenance order Dates tab ?
Q2 - in the PP-PM integration, what is the value on which the system is based? (is it the scheduled or the basic one).
Q3 - We want to monitor the time of the orders (is it a good practice to use the schedType Forwards with time)
Q4 - What is the use of the adjust dates key
Adjust basic dates, adjust dep. reqmts to operation date | |
1 | Adjust basic dates, adjust dep. reqmts to order start |
2 | Do not adjust basic dates, dep. reqmts to operation dates |
3 | Do not adjust basic dates, dep.reqmts to order start |
Thanks,
Karim Es.