Hello,
We have a situation where we created a general task list for Planning plant A, and are trying to add material to the components section of the task list that are maintained in Plant B. This is due to plant B completing this task for Plant A.
So when we add a material to the components section of the task list we get the error that the material is not maintained in Plant A. Plant B is the plant on the operation/work center level of this task list however the plant check happens to the planning plant (plant A) of the task list.
Does anyone know of any configuration we can change or maybe a user exit to change this plant check to happen on the operation/work center level of the task list rather than the planning plant of the task list?