CM24 - Scheduling more hours than available for overtime

$
0
0

We use CM24 for scheduling maintenance orders by personnel numbers. The HR work schedule attached to each person is 8hrs a day - 7 days a week. However once in a while an operator is given 2-4 hrs of overtime on the fly. In such scenario if the Scheduler tries to schedule a Work order for extra hours in the day, the work order gets pushed to the next day.

 

Is it possible to force a schedule to allow  extra capacity in such type of scenarios?