Hi experts,

 

I have one requirement from my Business for updating Basic Finish date based on the Material availability date

 

Requirement goes like this, When we enter a Component of 100 qty  in the service order , if stock is not available we get system status as MSPT and IWBK we can see how much quantity confirmed

 

But i dont see any table or report which shows when this material can be available for further delivery. Based on the next available material date i have to change the basic finish date in the service Order

 

Please let me know if you any report available for this or any standard approach. I want to know if any exist to leverage this functionality and logic how to get this accomplished

 

thanks

sarvan