Hi experts,
i need help regarding Capacity Planning & Scheduling of Maintenance order,
i have created a work center (MECH) with total operating time 8 hours, 100% utilization, 2 persons and total working time per working day is 16 hrs... then i have created a maintenance order and used that particular work center (MECH).Entered two operations in this order, for first operation i planned 8 hours work with one person and total calculated duration that was 4 hrs, for second operation, i entered again work 8 hrs, 1 person and duration 4 hrs. when i scheduled this order, the system scheduled them on two different dates although both of the operations should be scheduled on the same date.... please help me in this regard.