Hello All,
When creating a maintenance order (PM05) , i can not get the inspection lot created .
- Equipment category is production ressource/tool.
- Master inspection characteristics is in released status.
- Sampling procedure is created for PM.
-General task list created with inspection point at header level , with control key including inspection characteristic , with master inspection characteristic , with sampling procedure
- Configuration for inspection type and order type is done.
- In Task list Header inspection point 300 is maintained.
- In Task List Header usage and status are maintained as'4'.
-
When creating the order manually (or via a maintenance plan) : the order is created and released but with no inspection lot assigned...
Can anyone help me in finding out the solution?
Thanks in Advance,
Arun.