Hi,
I have a question related to single cycle plan. We have a 6 month single cycle plan scheduled with start of cycle 11/7/2013 and a call horizon 80% technically as per this the work order should be created 36 days prior to 05/06/2014 which is 03/31/2014 but the work order is created on 01/03/2014. Since we have batch job for IP30 which runs every week with a call interval of 30 days which means that the WO should have been created on 26-Feb but the WO has been created on 03-Jan.Can you suggest what caused the work order to be created that early?
Also
Thanks,
SP