Dear Experts,
I am facing an issue, I had created Plans with Multiple, items each item is having different task list following is the example of packages assign.
6m 1yr 2yr 5yr
Item A X X
Item B X X X
Item C X X
So if I am scheduling for Start in Cycle for 1 year its Creating Work order for Item B and Item C.
So my Question is It Should Generate Work Order for Item A after 1 year as its 6 Month is due.
Same if I am scheduling for Start in Cycle for 2 year its Creating Work order for Item A and Item B.
So my Question is It Should Generate Work Order for Item C after 2 years its 1 year is due.
So I considered that Plans is not Considering Individual Item and as per higher hierarchy in strategy. In this case to get a correct result I changed my Task list for above as
6m 1yr 2yr 5yr
Item A X X X
Item B X X X
Item C X X X
Is it correct method or there is another way to handle this scenario.
Thanks & Regards
Kamlesh